Reimagining Penn’s Largest Dining Café
1920 Commons is Penn’s largest dining café and was originally built as part of the 1971 campus expansion. This first full renovation will introduce a new entrance pavilion, expanded open-level space with multiple dining platforms, a 350-seat all-you-care-to-eat café, and additional retail locations. The renovation will also retain spaces the campus community values—such as the coffee café and market—while adding more areas for studying, connecting, and recharging in response to student preferences.
Schedule and Phasing
A phased construction approach will allow Penn Dining to continue operating from the building throughout the renovation in a reimagined capacity, ensuring service remains focused on the needs of students and the campus community. Construction will begin in Summer 2026, with the fully renovated 1920 Commons expected to be complete in Winter 2029.
Noisy work will occur 8 a.m. to 5 p.m. through December 2028. This noise will be heard in Harnwell College House.
Dates | Activity | Description of Work | Impact |
|---|---|---|---|
May 2026 through September 2026
| Phase 1A: Demolition | The project includes limited demolition to create a new opening between 1920 Commons and the planned addition, along with interior pre-construction work to prepare the building ahead of the academic year. Loud demolition activity is expected for approximately four weeks beginning in mid-May. A temporary wall will be installed by June 7 to enclose the construction area, allowing operations to largely resume as normal thereafter. During this phase, the Starbucks seating area—including soft seating and the lower-level patio—will be closed. | Demolition will be loud during working hours. Noise will be heard in both 1920 Commons and Harnwell College House. |
October 2026 through November 2027
| Phase 1B: Construction of Addition | This phase includes construction of the new addition, which will ultimately serve as the new entrance to 1920 Commons. Throughout construction, All-You-Care-to-Eat, Starbucks and Gourmet Grocer will remain open, and summer 2027 operations are expected to continue out of 1920 Commons. A temporary Grab-and-Go location will be constructed by the end of Phase 1B and is scheduled to open on the first day of classes in January 2028. | Construction will be loud during working hours. Noise will be heard in both 1920 Commons and Harnwell College House. |
December 2027 through July 2028
| Phase 2: Renovation of the Lower Levels
| This phase includes renovation of the lower level (Starbucks area) and first level (Gourmet Grocer) of 1920 Commons. Upon completion, the space will feature an enhanced Gourmet Grocer, a new retail location, a coffee shop, and new meeting and study spaces. During construction, a temporary Grab-and-Go—offering exchange and grocery items, including halal and kosher options—will operate from the lower level of the new addition. AYCTE will remain operational throughout the academic year and will close during the summer. | Noisy work will take place inside of 1920 Commons. |
May 2028 through November 2028
| Phase 3: Renovation of AYCTE cafe
| This phase includes the closure and renovation of the all-you-care-to-eat cafe, with operations supported through various on-site operations. | Noisy work will take place inside of 1920 Commons. |
| November 2028 through January 2029 | Phase 4 | This phase includes preparing to open the all-you-care-to-eat cafe. | Noisy work will take place inside of 1920 Commons. |